Our Recent Completed Project
KARADENIZ HOLDING
Date: Oct 2010 to Sept 2011
Projects Scope
GENERATOR SYSTEMS AND MSB SYSTEM IN P 888
- Completion 100%
Responsibilities and Service
Supervising.
Worker Handling.
Electrical Systems Wiring.
Electrical power cable termination.
Electrical power cable testing and commissioning.
NINGALOO VISION
Date: Oct 2010 to Sept 2011
Projects Scope
ELECTRICAL LIGHTING SYSTEM INSTALLATION & INSTRUMENT INSTALLATIONS
- Completion 100%
Responsibilities and Service
Worker Handling.
Electrical Systems Wiring.
Electrical power cable termination.
Instruments termination of Pressure transmitters & Temperature transmitters.
Instrumentation cable installation & Testing.
FPSO MODEC JUBILEE
Date: Oct 2010 to Sept 2011
Projects Scope
PIPERACKS 5, 6, 7 & 8
- Completion 100%
Responsibilities and Service
Electrical Cable ladder Supports & Cable ladder Installation.
Electrical & Instrumentation cable Earth & continuity checking.
Lighting installation with termination.
Fire & Gas System installation with termination.
PA/GA System Installation with termination.
FPSO BP ANGOLA
Date: Oct 2010 to Sept 2011
Projects Scope
PIPERACKS 7, 8, 9 & INLET SEPARATION MODULE
- Completion 100%
Responsibilities and Service
Electrical cable ladder and Tray installation.
Instrument installation for process control.
Electrical cable installation and Termination.
Chemical Injection, Fusible loops and Process Tubing Installation.
Oil and Pneumatic tubing and fitting installation.
Lighting installation with termination.
Fire & Gas System installation with termination.
PA/GA System Installation with termination.
Process Junction Boxes Installation with termination.
Installation and termination of Transmitters and Detectors
CONOCOPHILLIPS CONSTRUCTION SDN.BHD
Date: Nov 2011 to Mar 2012
Projects Scope
SPAS – Solar Panel Assembly System.
- Completion 100%
Responsibilities and Service
PCBA – Screw Fastening Unit
Cobra 10 Second Screw Fastening & Torque Checking Unit
Disc Assembly Unit
PLC Panel Assembly
Panel wiring designing
Machine Wiring
Instrumentation Tubing
Control and installation of PLC
VMEPROCESS PTE LTD AND KEPPEL & JURONG SHIPYARD
Date: Mar 2012 to April 2013
Projects Scope
> Erection of Power and Control system in Keppel Tuas, Singapore
>Erection of High tension Cables & Power Panels in Central Exercise in keppel
>Erection of Illuminators in Central Exercise of jurong shipyard
>Erection of Submarine Motors and Starter Panels in Jurong Shipyard
- Completion 100%
Responsibilities and Service
High tension & Low tension power Cable Wiring
High tension & Low tension panel Control Wirings
High tension Distribution Panel Termination
Domestic Buildings Wiring & Maintenance
Panel Wiring Designing
Panel Wiring and Termination
Control and Installation of PLC in Domestic Control
Control and Installation of Illumination devices
Control and Maintenance of Submarine Pumps & Control Panels
OFFSHORE CONSTRUCTION SERVICES
ELECPEC SDN BHD
Date: Nov 2011 to Mar 2012
Projects Scope
SPAS – Solar Panel Assembly System.
- Completion 100%
Responsibilities and Service
OSX WHPPDU module
Worker Handling
Electrical Systems Wiring
Electrical power cable termination
Instruments termination of Pressure transmitters & Temperature transmitters
Instrumentation Tubing
Instrumentation cable installation & Testing.
KEPPEL SHIPYARD TUAS
Date: Nov 2011 to Mar 2012
Projects Scope
SPAS – Solar Panel Assembly System.
- Completion 100%
Responsibilities and Service
PCBA – Screw Fastening Unit
Cobra 10 Second Screw Fastening & Torque Checking Unit
Disc Assembly Unit
PLC Panel Assembly
Panel wiring designing
Machine Wiring
Instrumentation Tubing
Control and installation of PLC
Checking and Troubleshooting of Controls
Control and installation of drivers.